
Airport Infrastructure Upgrades
Work with Bitarchitects on this upcoming project ready for construction
Project Scope of Work
The project involves providing all necessary design, permitting, environmental, and construction services for the replacement of three sanitary force mains.
I. General Requirements:
- Site investigation, testing, analysis, and utility locating.
- Full design and permitting for all work.
- Environmental testing and remediation services, including soil management and dewatering plans for potentially contaminated soil.
- Extensive stakeholder coordination with multiple parties.
II. Construction Packages:
A. Package #1: Base Work
- Replacement of approximately 300 linear feet of 12-inch sanitary force main and associated piping at the North Pump Station. This includes replacing the piping manifold within the dry-well and the discharge pipe from the pumps.
- Installation of a new 12-inch HDPE force main from the Pump Station discharge header to the property line.
- Replacement of approximately 350 linear feet of an 8-inch sanitary force main at the Roads Pump Station.
- Replacement of approximately 880 linear feet of a 12-inch sanitary force main to the proposed connection point.
- Installation of new valve vaults for future connection to Package #2.
- Maintenance-of-traffic and site restoration, including erosion and sediment control and tree/shrub protection.
B. Package #2: Alternate Work (within NPS property)
- Rehabilitation of approximately 2,468 linear feet of a 12-inch sanitary force main at the Pump Station using Cured-in-Place Pipe (CIPP) via trenchless utility construction.
- Rehabilitation of approximately 2,429 linear feet of an 8-inch sanitary force main at the Roads Pump Station using CIPP.
- Replacement of approximately 350 linear feet of a 12-inch sanitary force main near the Route 233 viaduct.
- Construction of a new manifold vault and a new sanitary force main crossing under the GWMP using jack-and-bore casing methods.
- Routing of the three force mains to the new manifold vault and connecting them to the existing 14-inch force main going under the CSX line.
- Verification of peak flows and overall system performance.
- Maintenance-of-traffic and site restoration, including temporary relocation.
III. Technical Requirements
- Methodologies: Use cut-and-cover for ductile iron pipe, jack-and-bore for pipes under roadways, horizontal directional drilling for HDPE pipe, and CIPP for trenchless rehabilitation.
- Outages: All work must be planned and coordinated for low-flow conditions to minimize interruption of sanitary flow. Bypass pumping and pump-and-haul operations will be required.
- Safety: The project requires a strong safety approach, including a low Experience Modification Rate (EMR) and Days, Away, Restriction, and Transfer (DART) rates.
- Environmental: Compliance with Virginia’s Erosion and Sediment Control and Stormwater Management regulations. Proper handling and disposal of assumed contaminated soil and water is mandatory.

